Fixed-Fee Performance Guarantee Remediation of Phase-Separated No. 2 Fuel Oil, Greater Boston, MA

By on December 27, 2019

Regulatory Agency: Massachusetts Department of Environmental Protection
Contaminants: Separate Phase #2 Fuel Oil and Dissolved Petroleum Hydrocarbons
Remediation: Dual Phase Vacuum Extraction
Treatment: Offsite Suspended Solids Separation; Oil/Water Separation; Granular Activated Carbon
Scope: Fixed-Fee to Site ClosureProject Summary

  • Based on the client needs, ESI completed the project on a fixed fee basis.
  • Alternative cleanup criteria were negotiated based on risk assessment of contaminants.
  • ESI designed and installed a high vacuum extraction system, which achieved remedial objectives within one year of operation.

Project Details

ESI committed to investigate, design, build, and operate a remediation program to meet regulatory requirements for closure under a fixed-fee contract.

Click to read more about this project